Powered Land in Florida, Who Pays for Power

Writer: Irving Diaz
Irving Diaz
4 days ago
6 min read

Updated: 4 hours ago

Under Florida's new rules, a site's value depends less on the megawatts nearby and more on who must pay to deliver them.


Powered land in Florida is acreage with a credible path to the large blocks of electricity that data centers need. It is pursued by data center developers, institutional investors and family offices, and it is offered by landowners who hold sites near transmission lines and substations.


The rules changed this year. Senate Bill 484, signed on May 7, 2026, requires every customer with a peak load of 50 megawatts or more to bear its own full cost of service. Florida's investor-owned utilities have filed large load tariffs or compliance filings with the Public Service Commission ahead of the October 1, 2026 deadline, and those filings are now under review.


Yet many owners still price land on proximity to power alone. The question buyers now underwrite is who pays to deliver that power, how much, and for how long. This article explains how the new framework shifts cost and risk, and what it means for owners and buyers deciding whether, and at what price, to transact.


Powered land in Florida: an electrical substation and transmission lines beside a cleared industrial development site in South Florida

What Florida's Data Center Law Requires

SB 484 created section 366.043 of the Florida Statutes. A large load customer is one with an anticipated monthly peak of 50 megawatts or more at a single location, measured over a 15-minute interval. Its full cost of service includes connection, incremental transmission, incremental generation, other infrastructure, and operations and maintenance. None of that cost may shift to other customers.


The statute lets utilities protect themselves with specific tools: contributions in aid of construction, minimum demand charges, incremental generation charges, financial guarantees, minimum load factors, take-or-pay provisions, and minimum-term contracts with early termination fees. It also bars splitting one site's load into smaller connections to stay under the threshold, and it bars service to entities controlled by foreign countries of concern.


The law reaches beyond the utility bill. Local governments keep full authority over zoning and land use for large load customers, and the governor's office said the law preserves their ability to reject projects. Water use permits for large-scale data centers require a hearing, and reclaimed water must be used where a suitable supply reaches the property line.


Large Load Tariffs and Who Pays for Power

Florida Power & Light, which serves most of South Florida, told regulators in an October 2026 filing that its rate framework approved in November 2025 already complies with the law. Under it, a large load customer funds an engineering study, pays 100 percent of any new generation built to serve it, builds and owns its substation, and pays up front for new or upgraded facilities. Contracts run a minimum of 20 years, with a minimum bill for reserved capacity and an exit fee if the customer leaves early.


Tampa Electric's September 30 filing shows how far the terms can reach. It proposes 20-year minimum contracts, three years' notice before termination, and collateral of up to $2 million per megawatt of contracted demand, depending on the customer's credit. Duke Energy Florida's proposed tariff is contested by the Office of Public Counsel, so its final terms remain open.


The direct answer is that the data center customer pays the utility. The practical answer is that the cost reaches the land. A buyer that must fund generation, a substation and years of collateral will underwrite those costs into what it can pay for the site.


How Powered Land in Florida Is Priced Now

Pricing now turns on documented delivery cost and timing rather than distance to a transmission line. Buyers weigh these factors first:


  • Available capacity. A utility's written statement of what the local system can serve, and when, carries more weight than a map of nearby lines.

  • Delivery cost. The engineering study's estimate of substation, transmission and generation costs is now a direct deduction from what a buyer can pay.

  • Timeline to energization. Years spent waiting for generation or transmission upgrades carry a holding cost that buyers price in.

  • Zoning and local posture. A site already zoned for the use, in a county that has signaled support, removes the largest discretionary risk the law preserves.

  • Water. Access to reclaimed water at the property line can shorten permitting and reduce opposition.

  • Load size. A use below 50 megawatts falls outside the large load definition, which can suit smaller sites in western Miami-Dade or Broward.

  • Buyer credit. Collateral requirements favor well-capitalized buyers, which narrows the pool and rewards a seller who qualifies buyers early.


The result is that two parcels the same distance from a substation can trade at very different prices. Pricing reflects verified capacity, documented delivery cost and the time and capital needed to energize the site.


Florida Data Center Land and Deal Structure

The law changes how contracts for data center land are written. A buyer cannot know its delivery cost until the utility completes an engineering study, so it will ask for a due diligence or option period long enough to receive one. Owners should expect that request and decide in advance how long they will hold a site off the market.


Study deposits, entitlement costs and extension payments become points of negotiation. A seller who funds part of the work can shorten the buyer's diligence and support a higher price, but takes on risk if the study disappoints. A seller who funds none of it keeps capital but accepts a longer, less certain process.


Confidentiality also has a firm limit. Florida law keeps a company's plans to locate a facility confidential for 12 months, and SB 484 removed the extension for data center projects. Owners should assume a project will become public within that window. A seller representation mandate that plans for that disclosure protects value; Diaz Commercial's seller representation is built around discreet, documented processes.


Diaz Commercial's development sites practice covers powered land and industrial land across Florida. For background on how data center sites are valued by capacity, see Data Center Real Estate, Measured in Megawatts.


What Owners Should Consider First

Can the utility confirm capacity in writing? A buyer will discount any claim of power that the utility has not documented. Owners who request a preliminary capacity review before marketing can present a basis buyers can defend.


Who will fund the engineering study, and how long will it take? The study sets the buyer's delivery cost and therefore its price. Agreeing on who pays for it and how long the buyer may take is often the central term of the contract.


Is the site's zoning secure? The law leaves local governments free to deny data center projects. A site with the use already permitted, or a clear path to approval, is worth more than one that depends on a future hearing.


Powered Land, Priced on Who Pays

Florida has decided that data centers must pay their own way. For owners of powered land in Florida, that shifts value toward sites with documented capacity, known delivery costs and secure zoning, and away from sites that offer only proximity. Owners and buyers who underwrite the full cost of power before they commit will hold a basis they can defend.


Sources




Diaz Commercial advises owners and investors on commercial real estate investment sales and debt advisory, from single assets to portfolios, with every engagement overseen by the firm’s principal from first conversation through closing.


Contact Diaz Commercial, PLLC at (954) 644-8900 or visit our offices at 2200 N. Commerce Pkwy., Ste. 200, Weston, Florida 33326.


Considering a sale or a financing? Speak with our team.



Diaz Commercial, PLLC is a Florida licensed real estate brokerage. This article is general information and is not legal, tax, or financial advice. Market conditions, financing, and pricing vary by property and should be reviewed with qualified professionals. Diaz Commercial is not a mortgage lender, mortgage broker, loan originator, securities broker-dealer, or investment adviser, and does not make loans or issue loan commitments. Its debt advisory services are limited to commercial real estate financing for business-entity borrowers, placed with institutional lenders; approval, terms, and timing rest with the lender. Nothing in this article is an offer to lend or to sell or buy securities.